Yerwada MHADA Colony Redevelopment Gathers Pace: Revised Layout Being Prepared for Over 90 Old Buildings

A revised layout is being prepared for the redevelopment of more than 90 buildings, about 40 years old, in the MHADA colony spread over around 75 acres in Yerwada. Work on a viability report for cluster redevelopment has also begun.

By Sham Rathi ·

Yerwada MHADA Colony Redevelopment Gathers Pace: Revised Layout Being Prepared for Over 90 Old Buildings

Work on redeveloping the old buildings in the MHADA colony at Yerwada has started to move ahead. The colony covers about 75 acres and has more than 90 buildings, built around 40 years ago. As the buildings have aged, residents' safety has become a concern, and residents want redevelopment to happen soon.

The Pune Housing and Area Development Board (MHADA, Pune board) has started following up with the state government on the matter. A letter from the board gives details of the permissions needed for redevelopment and the work on a revised plan. This information was shared by Balasaheb Janrao, state secretary of the Republican Party of India (Athawale).

Read also: Pune Grand Tour 2027: Ganeshkhind Road, Baner Road and Khadki Stretches Get New Surface and Footpaths. Deadlines and What Changes

Old layout, new rules

The colony stands on survey numbers 191-A-1 and 191-A-2 in Yerwada. Its layout was approved under the development plan sanctioned by the Pune Municipal Corporation on 30 October 1999. According to the board's letter, the site can get an FSI (floor space index) of 3.00 under the Unified Development Control and Promotion Regulations (UDCPR 2020).

However, the old layout has not been updated to match the new rules or the development plan approved in 2017. This is holding up redevelopment. To solve this, a revised layout is being prepared. Architects on the board's panel have been appointed to get it approved by the Pune Municipal Corporation and other authorities. The board says this work is in progress.

Height limits because of defence land and the airport

The colony falls in a restricted zone linked to the defence department and Lohegaon airport, so building heights here are limited. According to the Pune Municipal Corporation's height certificate, the limit is 566.50 metres plus 75.75 metres, that is, a total of 642.25 metres.

There are also restrictions on construction within 100 metres of the defence boundary. Getting no objection certificates (NOC) and technical approvals from the departments concerned will therefore be a key step in the redevelopment.

Cluster redevelopment option

Redeveloping all the buildings in the colony together could solve much of this problem. So the option of cluster redevelopment is being considered. The board's chief officer has stated in the letter that preparations are under way to submit a viability report after further orders from the authority.

What next?

  • Approval of the revised layout by the Pune Municipal Corporation and other authorities.
  • No objection certificates from the defence department and the airport authority.
  • A viability report for cluster redevelopment.

Actual redevelopment work can begin only after these approvals are in place. Balasaheb Janrao said local residents hope that MHADA itself will redevelop the buildings in small clusters, without bringing in private developers.

Questions and answers

How many buildings will be redeveloped in the Yerwada MHADA colony, Pune (2026)?

The Yerwada MHADA colony covers about 75 acres and has more than 90 buildings that are about 40 years old. Redevelopment is proposed for all of them.

What work is under way on the Yerwada MHADA colony redevelopment in Pune as of October 2026?

The Pune Housing and Area Development Board (MHADA Pune board) is preparing a revised layout under the new rules, and architects on its panel have been appointed to get it approved. Preparations for a viability report for cluster redevelopment have also begun.

What is the main hurdle in the Yerwada MHADA colony redevelopment in Pune (2026)?

The Yerwada MHADA colony falls in a restricted zone of the defence department and Lohegaon airport. So building heights are limited, and no objection certificates from the defence department will be needed.

Follow PuneDiary on Facebook Daily Pune news, events and updates in your feed. Join 13,000+ Punekars.
Filed under: City News

Share this story

More Pune news

Something wrong or missing on this page? Suggest a correction
Our team checks every suggestion before the page is changed.