Pune Grand Tour 2027: Ganeshkhind Road, Baner Road and Khadki Stretches Get New Surface and Footpaths. Deadlines and What Changes

PMC is racing to finish resurfacing, footpath and utility works on Ganeshkhind Road, Baner Road and roads to Khadki before the Pune Grand Tour cycling race in January 2027. Median works are due by 30 November and the rest by 31 December.

By Sham Rathi ·

Freshly resurfaced road under the Metro line in Pune ahead of the Pune Grand Tour 2027 AI-generated image
Roads on the Pune Grand Tour 2027 route are being resurfaced before January

If you drive on Ganeshkhind Road, Baner Road or towards Khadki, you have seen the digging, the new asphalt and the footpath work. All of it is for the Pune Grand Tour 2027, the international cycling race that will run on Pune roads in January 2027.

PMC Commissioner Naval Kishore Ram has been inspecting the route himself, and the city has set firm deadlines.

Read also: PMC Front Margin Drive: Shops That Reoccupy Cleared Space Will Be Sealed for Good. What Every Pune Shop Owner Must Know

Which roads are being fixed

Under Package One of the route works, PMC inspected these stretches:

  • Baner Road, from YASHADA to Ganaraj Chowk
  • Ganeshkhind Road
  • Bremen Chowk to Dr. Babasaheb Ambedkar Chowk
  • Khadki Railway Station to ABIL Chowk
  • Roads inside Khadki Cantonment

What work is being done

  • New asphalt surface
  • Manhole and chamber covers raised or lowered to match the new road level, so there are no bumps or dips
  • Footpaths repaired, and new footpaths where there were none
  • Damaged road dividers repaired, and dividers under the Metro line set in a straight line
  • Metro pillars painted
  • Electricity and other utility lines shifted where needed

PMC is working with PMRDA, Pune Metro and MSEDCL on these stretches, since parts of the road are under Metro construction.

The deadlines

  • 30 November 2026: median (divider) improvements on a 4.5 km stretch
  • 31 December 2026: all remaining works and corrections on Baner Road and Ganeshkhind Road

PMC had also said that agencies digging the race roads after 20 November would face a much higher penalty, so that new roads are not dug up again before the race.

What it means for you

  • Expect slow traffic and short diversions on these roads through December, especially when asphalt is being laid.
  • The good news: once finished, these roads should be smoother, with fewer bumps from manhole covers and better footpaths for walkers.
  • Seen a newly laid road being dug up again? You can report it to PMC through the PMC CARE app.

Questions and answers

Which Pune roads are being repaired for the Pune Grand Tour 2027 cycling race?

Under Package One: Baner Road from YASHADA to Ganaraj Chowk, Ganeshkhind Road, Bremen Chowk to Dr Babasaheb Ambedkar Chowk, Khadki Railway Station to ABIL Chowk and roads in Khadki Cantonment, among others on the route.

When will the Pune Grand Tour 2027 road works on Ganeshkhind Road and Baner Road be finished?

Median works on a 4.5 km stretch are due by 30 November 2026, and all remaining works and corrections on Baner Road and Ganeshkhind Road by 31 December 2026.

When is the Pune Grand Tour 2027 cycling race?

The Pune Grand Tour 2027 is planned for January 2027 on Pune roads.

What work is PMC doing on Pune Grand Tour 2027 roads?

New asphalt, matching manhole and chamber levels to the road, repairing and building footpaths, fixing dividers, painting Metro pillars and shifting utility lines.

Follow PuneDiary on Facebook Daily Pune news, events and updates in your feed. Join 13,000+ Punekars.
Filed under: City News

Share this story

More Pune news

Something wrong or missing on this page? Suggest a correction
Our team checks every suggestion before the page is changed.